|
Access Dispute Resolution Rules |
|
Joint Reference Submission to Timetabling Panel TTP100 re Service in Connection with Wootton Bassett Renewal August 2006 |
|
Network Rail First Great Western |
1
1
details of parties
1.1
1.1
The names and
addresses of the parties to the reference are as follows:-
(a)
First
Greater Western Ltd., whose Registered Office is at Milford House, 1 Milford
Street, Swindon SN1 1HL (“FGW” ("the Claimant")); and
(b)
Network
Rail Infrastructure Ltd, whose Registered Office is at 40 Melton Street, London
NW1 2EE (“NR” (“the Respondent”))
2
The Parties’ right to bring
this reference
2.1
This
matter is referred to a Timetabling Panel ("the Panel") for
determination in accordance with Condition 5.1.1.1 (c) of Part D the Network
Code.
2.2
Part
D of the Network Code includes the following relevant conditions:


![]()

D4.8
is the Supplementary Timetable Revision Process;

![]()




3 Contents of reference
The
Parties have together produced this joint reference and it includes:-
(a)
The
subject matter of the dispute in Section 4;
(b)
A
summary of the issues in dispute in Section 5;
(c)
A
detailed explanation of the issues in dispute prepared by the claimant with a
paragraph by paragraph response from the respondent(s) in Section 6;
(d)
Any
further issues raised by the respondent in Section 7;
(e)
The
decisions of principle sought from the Panel in respect of legal entitlement
and remedies in Section 8; and
(f)
Appendices
and other supporting material.
4
subject matter of dispute
4.1 This
referral arises because FGW disputes NR alleged right to flex its services
after the date by which FGW believes the deadline for such flexing right has
passed.
It
concerns the flexing of three FGW services already diverted via the Berks and
Hants as a result of the renewal of Wootton Bassett Junction and the flexing of
an FGW normally operating on the route.
The
diversions are occurring as a result of a possession that is taking place in
August rather than at Christmas mainly in order to assist the maintenance of
coal traffic to Didcot Power station during the winter months. Trains already
diverted because of this are now being retimed to accommodate a stone train
operated, FGW believes, by the same freight company.
The
FGW trains diverted are key long distance commuter and business services from
South Wales and the Bristol area to Reading and London and have extended
journey times, some by an hour or so. The new timings add a further 12 minutes
to one, 4 to another and 6 to a third. In addition they add 8 minutes to a
previously unaffected Bedwyn - Newbury - Paddington service. These further
retimings will require some minor adjustment to driver diagrams as one break is
broken by the further delay.
4.2 The FGW diversionary paths
were offered by NR on 7th July. These were accepted by FGW and published. All
trains included in the offer to FGW were offered such that “all of these
schedules have been accepted and published today”. It also contained a caveat
that due to “some outstanding discrepancies with the Freight Company’s Offer
all the attached timings may be subject to change and FGW will be notified accordingly if this occurs.”
On
18th August (after the timetable for the days of implementation, Tuesday 29th
August to 1st September had been published in public pamphlets and on FGW’s
website) NR sought to seek FGW’s permission for further retimings. This was
rejected the same day on the grounds of additional delay to services already
published.
FGW
believes there is no scope for such retimings to be imposed given FGW’s
rejection and clauses 4.8.7 and 4.7.2
which it believes taken together show the deadline for such changes as a result
of a possession already declared and planned under the supplementary timetable
process as this was is seven weeks prior to implementation.
5
summary of dispute
Network Rail
believes that in caveating the 7th July offer to FGW that further
freight service validation might impact upon FGW services, the decisions
notified to FGW on the 18th August are valid and the subsequent retimings
of 4 FGW services should be accepted. [Please see Appendix 1 e-mail]
FGW,
however, believe that this imposition of retimings on 4 services is
unacceptable at this stage of the process. [Please see Appendix 2 e-mail]
6
explanation of each issue
in dispute with response
EWS
have level one contractual rights to a Westbury to Acton freight service
(7A09). This train runs SX and loads to over 4,000t and thus is a difficult
service to path. The level 1 rights are for an 11.30 arrival at Acton with a
flex of plus/minus 30 minutes.
Network Rail has worked hard to satisfy all
parties contractual rights and in doing so believes that the amendment to the 4
FGW services are in line with the caveat attached to the 7th July
offer.
The Operational Planning teams are working
hard to see if a further amendment can be made to the 7A09 path to enable a
reduction in the retimings to the FGW services.
The 4 trains in question have been retimed
as follows:-
The retimings apply for 4 days next week
Tuesday to Friday and NR have offered to publically advertise the services in
line with FGW publicity.
If 7A09 is late then it will be regulated to
minimise overall delay and if it loads to a lighter weight than timetabled then
it arrive at the key location of Hungerford earlier and 1Z84 will run early
from that point.
7
any further issues raised
8
decision sought from the
PANEL
8.1
The
Panel is asked by FGW to determine:
that NR has no power to impose the retimings
sought on 18th August, and that timings issued on 7th July and currently
implemented should apply in the wtt for the four days concerned.
8.2 The Panel is asked by NR to ratify that
NR has correctly applied the flexing right as per the Decision Criteria and
that the amended timings provided subsequent to the caveatted offer on 7th
July should apply next week.
signatures
For and on behalf of l For
and on behalf of l
__________________________________________ _____________________________________
Signed Signed
__________________________________________ _____________________________________
Print name Print
name
Position: ______________________________ Position: _________________________
Date: ______________________________ Date: _________________________
9
Appendices and Annexes
Appendix
1 – copy of e-mail from Network Rail to FGW caveating the 7th July
offer
Appendix
2 – copy of e-mail from FGW to Network Rail rejecting the changes