ACCESS DISPUTES COMMITTEE
References for hearing by an
Access Dispute Panel
(from
April 2005)
Click on link in “Ref’ce
no.” Column to display the determination.
When finished click on
“Back” in your Browser to return to this list.
Last Updated 18 July 2011
Note:
the “Date” column indicates (if shown in brackets) the month that the
reference was notified to the Committee;
or, if not in brackets, it indicates the date of the hearing
|
Ref’ce
no. |
Determination PDF
File |
Date |
Reference from |
Subject |
Joint submission from the parties |
|
ADP1 (AD41) |
|
(Oct. 04) |
Central
Trans |
Notice pursuant
to the Network Code, Condition L7.1, re Local Output Commitments (STAYED pending the outcome of the appeal to the ORR against
determination AD40; and then withdrawn by referrer) |
|
|
ADP2 (AD42) |
|
(Oct. 04) |
Wessex
Trains |
Notice pursuant
to the Network Code, Condition L7.1, re Local Output Commitments (STAYED pending the outcome of the appeal to the ORR against
determination AD40; and then withdrawn by referrer) |
|
|
(AD43) |
01.06.05 |
Thameslink Rail
and Network Rail |
Compensation
for an unplanned possession resulting from flooding in Kings Cross tunnel Note:
Network Rail referred the Panel’s determination on appeal to an arbitrator –
see arbitration A18 |
|
|
|
ADP4 (AD44) |
|
(Mar. 05) |
First ScotRail |
Notice pursuant
to the Network Code, Condition L7.1, re Local Output Commitments (settled out of court) |
|
|
ADP5 (AD45) |
|
(Apr. 05) |
Eurostar (U.K.) |
Notice pursuant to
the Network Code, Condition L7.1, re Local Output Commitments (STAYED pending the outcome of the appeal to the ORR against
determination AD40; and then withdrawn by referrer) |
|
|
ADP6 (AD46) |
|
(Apr. 05) |
Network Rail |
Payment
of Access Charges in respect of Euston Station (settled out of court) |
|
|
(AD38) |
06.07.05 |
Network
Rail |
Delay
Attribution: allocation of delay responsibility
for incidents in the circumstances where a train is operated by different
Train Operators for portions of a through journey |
|
|
|
16.08.05 |
West Coast Trains |
Level
of compensation payable pursuant to Part G of the Network Code in respect of costs of bus
substitution during a period of West Coast Main Line possessions |
|
||
|
ADP9 |
|
(May 05) |
Midland Mainline |
Alleged Network Change |
|
|
(NV79 NV80) |
02.08.05 |
Freightliner
Group |
Claim
for costs of increased resources to be incurred due to diversions
necessitated by proposals in the WCML Major Project notice for 2005-2006 |
|
|
|
14.11.05 |
New
Southern Railway and Network Rail |
Delay
Attribution: allocation of delay responsibility due to external electrical
interference affecting rolling stock |
|
||
|
ADP12 |
|
(Nov.05) |
Freightliner
Heavy Haul
|
Vehicle
Change: operation of trains with increased length
between Humber and Kingsbury (settled out of court) |
|
|
20.02.06 |
Network Rail (and
EWS) |
Network Change:
Remodelling of Rugby station area |
|
||
|
|
22.02.06 |
First/Keolis Transpennine
Express |
Vehicle Change:
proposed introduction of Class 185 trains Note that the
determination was referred on appeal to the Office of Regulation, in its
decision (issued in August 2006) the
ORR ordered that clause 26.8.2 of the determination be struck out; the determination displayed here
accordingly has the clause struck out and the remaining sub-clause 26.8.1
subsumed into 26.8 |
|
|
|
ADP15 |
|
(Jan 06) |
Network
Rail (and Thameslink Rail) |
Network Change:
Imposition and removal of a temporary speed restriction at Silkstream
Jcn, Hendon (withdrawn by referrer) |
|
|
12.04.06 |
First Great
Western Link |
Delay Attribution:
Paddington |
|
||
|
ADP17 |
|
Hearing on 09.08.06 but adjourned |
Silverlink Trains
Services |
Network
Code, Part E – effluent contamination at Euston station platforms (settled
out of court) |
|
|
09.08.06 |
Silverlink Trains
Services |
Network
Code, Part E – oil contamination at Barking station platform |
|
||
|
11.10.06 |
First ScotRail |
Delay Attribution for an incident at Croy
on 26.09.05 |
|
||
|
|
24.1.07 |
First Great Western |
Interpretation
of Schedule 4 of First Great Western’s Track Access Agreement The
Panel’s interim determination was appealed to the Office of Rail Regulation
by Network Rail. In October 2007 ORR
delivered its judgement. The
Parties subsequently resolved the issues without further Panel involvement |
The
Appendices to this joint submission may be obtained upon application to the
Committee Secretary. There are technical problems regarding showing them on
the website |
|
|
ADP21 |
|
16.11.06 |
First Capital
Connect |
Whether a programme of East Coast Main
Line rewiring works should be classified as a Major Project.
First Capital Connect
subsequently pursued the matter of compensation to arbitration – see
arbitration A23 for Award as to Jurisdiction –
after which the parties settled the issue between themselves. |
ADP
21 Joint Reference |
|
ADP22 |
|
(Oct.06) |
Network Rail |
Network Change – referred under
Condition G2.4(a) – reinstatement of Rail Crossing at Porthmadog (withdrawn by Network Rail after Arriva Trains Wales confirmed
it had received sufficient information about the proposed Network Change) |
|
|
ADP23 |
Link to Annexe to
Determination |
07.08.07 |
Network Rail |
Part J;
Changes to Access Rights, Portbury – Rugeley PS The Panel’s determination was appealed to
the Office of Rail Regulation by Network Rail and Freightliner Heavy Haul. In
January 2008 ORR delivered its judgement.
|
|
|
ADP24 |
|
(June 07) |
First Great
Western |
Contention that proposed possessions at
Airport Jn warrant the issue of a Possession Strategy Notice (settled out of court) |
|
|
ADP25 |
|
(June 07) |
Network Rail |
Part J; Changes to Access Rights, Flows to
Ratcliffe and Ironbridge PS (settled
out of court) |
|
|
ADP26 |
|
(July 07) |
Network Rail |
Part J; Changes to Access Rights, Peak
Forest to Attercliffe and Hitchin (settled out of court) |
|
|
ADP27 |
|
(Mar. 07) |
Silverlink Train
Services |
Level of compensation payable in
connection with possessions at Stratford (change of Panel jurisdiction from
TTP126) (settled
out of court) |
|
|
ADP28 |
|
(Oct. 07) |
Network Rail |
Part J; Surrender of Access Rights, Lawley Street – Tilbury (settled out of court) |
|
|
ADP29 |
|
(Oct. 07) |
Network Rail |
Part J; Surrender of Access Rights, Grain – Crewe (settled out of court) |
|
|
ADP30 |
13.02.08 |
First Capital Connect |
Delay
Attribution for an incident at Elstree on 24.04.07 |
||
|
ADP31 |
|
01.02.08 |
Vehicle
Change: Costs and payment method for utilisation of Class 142 units in the
Bristol and Exeter areas Network Rail
lodged an appeal with the Office of Rail Regulation against the Panel’s
determination. |
||
|
ADP32 |
|
(June 08) |
New Southern Railway |
Station Access
Conditions: Responsibility for
settlement of charges arising out of leaks from the water supply to Arundel,
Chichester and Lewes stations (withdrawn by referrer) |
|
|
ADP33 |
Hearing commenced 29.10.08 and was adjourned |
29.10.08 |
Network
Rail’s Offer for the Principal Timetable, December 2008 (change of Panel
jurisdiction from TTP243) (withdrawn
by the referrer following ORR decision in respect of section 22A Railways Act
application, which removed the need for this matter to be determined by a
Panel) |
||
|
ADP34 |
|
(Jan.09) |
Non payment
by NXEC Trains of Station Access charges for use of Stevenage station (settled
out of court) |
|
|
|
ADP35 |
14.09.09 |
2006/07
Access charging at certain Major Stations Panel hearing
held jointly with ADP36 and ADP38 |
Network
Rail submission Part 1 Network
Rail submission Part 2 Network
Rail submission Part 3 Network
Rail submission Part 4 Network
Rail additional submission |
||
|
ADP36 |
14.09.09 |
2006/07
Access charging at certain Major Stations Panel hearing
held jointly with ADP35 and ADP38 |
See ADP35 |
||
|
ADP37 |
|
(Apr. 09) |
Provision of
access to information regarding 2008/09 utilities charging at certain Major
Stations (settled out
of court) |
|
|
|
ADP38 |
14.09.09 |
First Capital Connect, First
Greater Western, First/Keolis TransPennine, First ScotRail & Hull Trains |
2006/07
Access charging at certain Major Stations Hull Trains subsequently withdrew from
the dispute Panel hearing held jointly with ADP35 and ADP36 |
See ADP35 for
Network Rail submissions |
|
|
ADP39 |
08.07.09 |
First ScotRail |
Delay
Attribution for reduced speed running during fog on 13.04.07 |
||
|
ADP40 |
ORR’s
directions following appeal determination ORR’s
reasons for directions issued following appeal determination |
14.10.09 |
First ScotRail |
Whether new
engineering works policy for the West Coast Main Line should be classified as
Network Change Network Rail appealed to ORR against the
determination of the Panel hearing |
|
|
ADP41 |
11.11.09 |
First ScotRail |
Part J; use
of Train Slots across the Forth Bridge |
||
|
ADP42 |
|
25.11.09 |
Network Rail |
Part J;
Change to Access Rights, Mossend Euroterminal to Georgemas Jcn (train 4H44) DB Schenker
Rail (UK) lodged an appeal with ORR against the determination of the Panel
hearing |
Submission by Direct
Rail Services |
|
ADP43 |
|
(Oct. 09) |
Network Rail |
Part J;
Change to Access Rights, Daventry to Grangemouth (Settled
out of court) |
|
|
ADP44 |
|
25.11.09 |
Network Rail |
Part J;
Change to Access Rights, Mossend Euroterminal to Georgemas Jcn (train 6H44) DB Schenker
Rail (UK) lodged an appeal with ORR against the determination of the Panel
hearing |
Submission by Direct
Rail Services |
|
ADP45 |
|
(Nov 09) |
Arriva Trains Wales |
Network
Change: Cardiff Area Signalling Renewal (Settled out
of court) |
|
|
ADP46 |
|
21.01.10 |
Network
Rail |
Delay
Attribution for an incident in the Swanwick - Hamble area on 28.11.08 (Settled out
of court) |
|
|
ADP47 |
11.02.10 |
GB
Railfreight |
Access
charges in relation to the approach to Doncaster Railport |
||
|
ADP48 |
|
(Dec 09) |
Network
Rail |
Interpretation of “repair” and “maintenance” in
relation to Retail Telecomms (CIS and CCTV) at Franchised Stations where
First Capital Connect, First Greater Western and First ScotRail are SFOs First ScotRail items were subsequently
withdrawn from the dispute |
|
|
ADP49 |
|
25.02.10 |
XC
Trains |
Diversionary
arrangements via Lichfield (Withdrawn by referrer during the course of the
Panel hearing following provision of necessary assurances from Network Rail
regarding relevant possession arrangements) |
Annex
F to joint submission, Part 1 |
|
ADP50 |
24.03.10 |
Rail
Express Systems |
Refusal of
Access to Wembley Central station |
||
|
ADP51 |
|
(Feb 10) |
Network
Rail |
Part J;
changes to Access rights, mail trains (Settled out
of court) |
Joint
submission – Part 2
|
|
ADP52 |
14.04.10 |
GB
Railfreight |
Part J;
changes to Access rights GB
Railfreight submitted an appeal to ORR in relation to this reference but this
was done outside the prescribed time limit so not accepted |
||
|
ADP53 |
|
(Apr 10) |
Network
Rail |
Part J; Change
to Access Rights, Mossend Euroterminal to Georgemas Jcn/Inverness (trains
4H44 and 6H44) (Settled out
of court) |
|