2.![]()
IN
THE MATTER OF THE ARBITRATION ACT 1996
AND
IN THE MATTER OF THE ACCESS DISPUTE RESOLUTION RULES
AND
IN THE MATTER OF AN ARBITRATION
BETWEEN:
ARRIVA TRAINS NORTHERN LTD (FORMERLY KNOWN
AS NORTHERN SPIRIT L TD)
Claimant
-and-
RAIL
TRACK PLC
(IN RAILWAY
ADMINISTRATION)
Defendant
INTERIM
AWARD
INTRODUCTION
1. The
Claimant is a franchised train operating company. The company was
incorporated in December
1995 as Regional Railways North East Ltd. The company
changed its name on 11th
June 1998 to Northern Spirit Ltd. It changed its name again
on 25th April
2001 to Arriva Trains Northern Ltd. The company is referred to in this
award as "A TN".
3.
In 1996, A TN
required access over railway track infrastructure including a stretch of line
at Darnall known as Handsworth Cutting on the Sheffield to Cleethorpes Line.
4.
Since
privatisation of the rail industry, the Respondent ("Rail track") has
been and it was in 1996 the owner of railway track infrastructure including
Handsworth Cutting.
5.
In and since
1996, ATN have had access over parts of Railtrack's railway infrastructure
including Handsworth Cutting pursuant to a Track Access Agreement dated 28th
March 1996 ("the Track Access Agreement"). That agreement
incorporated by reference the Railtrack Track Access Conditions 1995 (as
modified from time to time) and the Access Dispute Resolution Rules, which form
the appendix to those Conditions.
6.
By Clause 8.2
of the Track Access Agreement, Railtrack are obliged to indemnify A TN against
loss and damage incurred or suffered by it as a result of a failure by
Railtrack to comply with its Safety Obligations (as defined).
7.
By Clause
11.1 of the Track Access Agreement, any dispute arising under Clause 8 is to be
resolved by mediation followed, if necessary, by arbitration pursuant to the
Access Dispute Resolution Rules.
2
7. On
18th September 1996, one of ATN's trains became derailed when
travelling from
Sheffield to Lincoln through
Handsworth Cutting. The derailment gave rise to
personal injuries sustained
by two members of ATN's staff and to extensive damage
to rolling stock.
8. Following
the derailment, a dispute arose between the parties as to whether Railtrack
were obliged to indemnify A
TN in respect of loss and damage incurred in respect of
such personal injuries and
damage to rolling stock pursuant to Clause 8 of the Track
Access Agreement.
9. The
dispute not being resolved by mediation, the parties agreed to appoint me, John
Marrin QC, as Arbitrator to
determine that dispute pursuant to Clause 11.1 of the
Track Access Agreement,
which appointment I accepted by letter dated 20th October
2000.
10. On
2nd, 3rd, 4th and 5th October 2001,
a hearing took place at which the parties
presented written and oral
argument and evidence. At that hearing, A TN adduced
evidence of fact from its
Deputy Managing Director, Mr Stuart Baker. It also
adduced expert evidence from
Dr Alan Clark, the Director of Geotechnics and
Underground Engineering of
Messrs High-Point Rendel (Consulting Engineers).
Railtrack adduced of fact
from the following witnesses:
(i) Mr
Alistair Cook, a Chartered Civil Engineer, who was, in 1996, Railtrack's
Structures Engineer for the
combined London North Eastern Zone ("LNEZ") and also the Railtrack
Director's Nominee for all Group and Line Standards.
(ii) Mr David Clarke, a Chartered Engineer, who was, in 1996, the
Permanent
Way Maintenance Engineer for
the area which included Handsworth Cutting, in the employment of Jarvis Rail
Ltd ("Jarvis").
(iii) Mr Les Turner who was, in 1996, an Assistant Section Manager
working
under the supervision ofMr Clarke.
(iv) Mr
Keith Burgess, who was, in 1996 and still is a Track Chargeman employed
by Jarvis and also
supervised by Mr Clarke.
(v) Mr
David Anderson, a Civil Engineer, who was, in 1999, responsible for the
supervision of certain
remedial works at Handsworth Cutting whilst in the employment of his former
employer's Messrs Thorburn Colquhoun.
(vi) Mr
Kenneth Haywood, a Chartered Civil Engineer, who was responsible for
earthwork structures within
the LNE Zone from August 1997 to September 2000.
Railtrack
adduced expert evidence from Mr Charles Laird, a Chartered Engineer, a Director
of Buchanan (CE) Ltd (Consulting Engineers) and, formerly, an Associate
Director of Messrs Thorburn Colquhoun Ltd ("Thorburn").
4
11.
At the
hearing, A TN were represented by Mr Christopher Jackson and Ms Ann Metherall
of Messrs Burges Salmon, Solicitors, and Railtrack were represented by Mr
Martin Soloman of Messrs Hay & Kjlmer,
Solicitors. I record my grateful thanks to those representing the parties for
their clear and concise submissions.
12.
On ih October 2001 a railway administration order
was made in relation to Railtrack and joint special railway administrators were
appointed. The effect was that, pursuant to s.ll (3) of the Insolvency Act
1986, the proceedings in this reference were stayed. Subsequently, the
Railtrack Administrator lifted that stay and notice to that effect was
delivered on 22nd October 2001.
13.
Having now
considered the arguments and evidence placed before me, I hereby make my
Interim Award, determining the substance of the dispute between the parties as
follows.
FINDINGS
The
Incident
14.
At 5 :21 am
on 18th September 1996, the Sheffield to Lincoln train was derailed
when it hit a large boulder which had fallen some time before from the North
side of Handsworth Cutting onto the track and had come to rest in the space
between the rails ("the four foot") of the up line. The boulder became
wedged between the underframe of the leading vehicle and the track. The train
then travelled approximately 160 yards before coming to a halt with all wheels
of the leading vehicle derailed. The trailing
5
vehicle remained on the
rail. The train was travelling at approximately 45 mph when it hit the boulder.
15.
Both the
driver, a Mr Slocombe, and the conductor, a Mr Barker, suffered bruising,
strains and post-traumatic stress disorder. There were no passengers on the
train.
16.
It was fortunate
that the train derailed to the left, that is, into the area at the side of the
track known as "the cess" and not to the right, that is, into the
space between the two tracks known as "the 6 foot". Had the train
derailed into the 6 foot, the consequences of the accident might have been much
worse since the train might have come to rest in the path of oncoming traffic
and caused a collision.
17.
Both Mr
Slocombe and Mr Barker made claims against ATN, which were managed by a claims
handler, Messrs Miller Fisher. Those claims were settled at a total cost to A TN of £18,367.82.
18.
The leading
vehicle of the train suffered significant damage and there was minor damage to
the trailing vehicle. The total cost of repairs to A TN was £152,156, against
which A TN allow a credit of £1 0,000 as required by Clause 16 of the Claims
Allocation and Handling Agreement dated 151 April 1994, by which it
is bound and which limits recoverable claims for damage to property to losses
in excess of £1 0,000.
19.
ATN's claim
to an indemnity under Clause 8 (2) of the Track Access Agreement is,
accordingly, for the principal sum of £160,523.82 plus interest. Railtrack admit
the principal sum, subject to liability.
6
The
Cause of the Incident
20.
As indicated
above, the immediate cause of the incident was a boulder which had fallen onto
the track. It had come to rest a few feet to the west of the 44 mile post. That
point is approximately half-way along the length of Hands worth Cutting.
21.
The cutting
was excavated into the natural bedrock of the Middle Coal Measures and
penetrates a sequence of mudstones and sandstones. The mudstones are more prone
to weathering than the sandstone, which results in stronger prominent sandstone
horizons with near vertical faces underlain by weaker mudstones, which
generally form shallower slopes. As the mudstone deteriorates, the products of
the weathering process tend to move down slope under gravity. The process
progressively reduces the support to the overlying harder sandstone horizon.
Eventually, the process leads to rotation of the sandstone blocks and toppling
failures, particularly where the overlying rock is jointed.
22.
In the
vicinity of the 44 mile post, the foot of the slope adjacent to the up line
comprises an exposed horizon of sandstone with a roughly vertical face of
approximately 2 metres in height. Above that, there is a stratum of mudstone
sloping at about 40 degrees and extending upward some 13 metres vertically.
Above that, there is a further horizon or ledge of sandstone ("the
sandstone ledge"), with an exposed face of up to 1.5 metres in its
vertical dimension. The boulder which caused the derailment became detached and
fell from this ledge.
7
23. The
fact that the boulder reached the track at all caused some surprise. In
particular
this is because the cess at
that location is unusually wide, measuring some 6 metres
approximately. Furthermore,
the depth of ballast on which the track is laid is
unusually thick at that
location. For these reasons, there was some question as to how
the boulder could have
reached the four foot of the up line.
24. The
explanation is that there was, by chance, a section of rock which protruded
outward from the vertical
face of the lower sandstone horizon at the foot of the
Cutting. Having become
dislodged and fallen down the slope, the boulder struck this
protruding section of rock and
bounced so as to land in or roll into the four foot.
Safety Obligations and
Group Standards
25. Upon
rail industry privatisation in 1994, Railtrack assumed responsibility for the
maintenance and renewal of
the network infrastructure.
26. Sections
2 to 4 of the Health & Safety
at Work Act 1974 ("HSW A") required
Railtrack to take safety
measures in the following terms:
"2(1) It shall be the duty of every employer to
ensure, so far as is reasonably practicable, the health, safety and welfare at
work of all his employees.
3(1) It shall be the duty of evelY employer to conduct
his undertaking in such a way as to ensure, so far as is reasonably
practicable, that persons not in his employment who may be affected thereby are
not thereby exposed to risks to their health or safety.
8
4(2) It shall be duty of each person who has, to any extent, control of
premises to which this section applies or of the means of access thereto or
egress there from or of any plant or substance in such premises to take such
measures as it is reasonable for a person in his position to take to ensure, so
far as is reasonably practicable, that the premises, all means of access
thereto or egress there from available for use by persons using the premises,
and any plant or substance in the premises or, as the case may be, provided for
use there, is or are safe and without risks to health".
27. Further,
the Management of Health & Safety
at Work Regulations 1992 ("the 1992
Regulations"), by
paragraph 3, required Railtrack to make risk assessments in the
following terms:
"3(1) Every employer
shall make a suitable and sufficient assessment of
(a) the risks to health and safety ofhis
employees to which they are
exposed whilst they are
at work; and
(b) the risks to the health and safety of
persons not in his
employment arising out of
or in connection with the conduct by him of his undertaking,
for
the purpose of identifYing the measures he needs to take to comply with the
requirements and prohibitions imposed upon him by or under the relevant
statutory provisions.
3(3)
Any assessment such as is referred to in paragraph (1) or
(2) shall be reviewed by the employer or
self-employed person who made it if:
(a) there is reason to suspect that it is no
longer valid; or
(b) there has been a significant change in the
matters to which hit
relates ".
28. The
Railways (Safety Case) Regulations 1994 ("the 1994 Regulations")
required
Railtrack to have and
maintain an approved safety case setting out the details of the
9
safety management system
used to control risk in its operations. The 1994
Regulations also conferred
upon Railtrack the role of Infrastructure Controller. In
that capacity Railtrack was
required to approve the safety cases of operators on the
rail network and also to set
up a separate ann, the Safety & Standards
Directorate, to
act as the custodian of the
operating rules known as group standards and which
imposed mandatory
requirements on those using the network.
29. Railtrack's
Railway Safety Case was dated March 1996. The executive summary
included the following
passage:
"The
Railway Safety Case demonstrates Railtrack's competence to discharge the responsibilities
of an Infrastructure Controller required by the Railway (Safety Case)
Regulations 1994.
It is based on:
·
the
adoption of mandatory Railway Group Standards by all parties operating on or
undertaking any activity on Railtrack's infrastructure;
·
the
implementation by Railtrack of a robust Safety Management System, modelled on
best UK industry practice;
·
the
Control of risks by the application of modern techniques to the Railway Group's
activities confirming those identified by BR's wealth of operating experience ".
At paragraph 7.23 under the
heading "Infrastructure Design, Installation and
Maintenance
Arrangements", the safety case continued as follows:
"7.23 Railtrack will own and control the national
mainline railway infrastructure. It will be responsible for the design,
installation and maintenance of track, signalling, electrification systems,
level crossings and operational buildings, tunnels, viaducts, bridges and
10
other
such structures together with the major stations given in Paragraph 5.4. Railtrack will be responsible for
the safety of cuttings, embankments, bridges, sea walls to the same extent that
BR was previously responsible n.
At
paragraphs 10.49 and 10.50 under heading "Organisation", the safety
case
continued as follows:
"10.49 The Controller, Safety Standards will
produce Railway Group Standards which will apply to the Railway Group. They
will be high level, designed to state what must be done, but not how to do it.
There will also be a few Railway Group Codes of Practice which will guidance on
how to achieve the associated standard.
10.50 There are many existing standards which were
produced by BR's Group Standards Organisation (GSO). Many of them tend to be
prescriptive and incorporate BR business requirements as well as safety and
interworking requirements. These have been reviewed, and some 4,000 will be
developed into high level Railway Group Standards. This programme will take
three to four years. The review process involves ensuring that they are
suitable for adoption by members of the Railway Group who have a contractual
relationship with each other, and that legal opinion on each has been obtained
by Railtrack. Until this process has been completed for a standard, the
existing standard will remain in effect".
30. Condition
3(2)(c) of Railtrack's Network License dated 31st March 1974
required
Railtrack to comply with all
relevant group standards.
Ais Gill
31. In
January 1995, there was a landslip at Ais Gill on the Settle and Carlisle line.
The
site had no previous history
of instability. The landslip caused the derailment of an
ATN train. The derailment
caused a collision in which an A TN employee was killed.
An enquiry was held in
February 1995 and the resulting report was published on 13th
March 1995. To some extent,
the incident focussed the attention of those concerned
11
with safety in the industry
upon the possibility that even those sites with no known
history of instability could
give rise to a significant safety risk. The difficulty of
identifying the sites most
likely to give rise to risk was highlighted in the Inquiry
Report at paragraph 3.1.4 in
the following terms:
"3.1.4 The question of risk assessment for
cutting slopes is a difficult one. On the one hand it seems wrong that the only
cuttings treated as 'at risk' are those with a history of slips. However, the
historical period, depending on records, is potentially very long, given the
age of the railway. The cutting slope at the site had presumably stood without
problem since the line opened in 1876.
Nonetheless,
mindful of the need to be proactive, the panel spent some time seeking a simple
formula to identify those cuttings most likely to be at risk, but were unable
to find a solution. This aspect seems worthy offurther consideration ".
The
Development of Group Standards
32. At
the date of the Ais Gill incident, the requirements for the inspection of
Railtrack' s
permanent way were embodied
in a group standard entitled "Track Maintenance
Handbook" and given the
number GClEH0005
("Handbook 5").
This included
provisions as follows:
(i) By
paragraph 8.6 in Section B under the heading "Track Inspector" the
following:
"8.6 The Track
Inspector will observe the conditions prevailing between and at the Board's
boundaries and identify future maintenance requirements for track components,
drainage, fencing, earthworks and line side management ..... The Track Inspector will
personally inspect bridges and other structures ... and report any
abnormal conditions found to the Engineer".
12
(ii) By
paragraph 3.1 in Section C under the heading "Cutting and
Embankments"
the following:
"3.1 All cuttings must be regularly examined,
particularly after severe frost, heavy rainfall or snow thaw, to check whether
rock, chalk or other material has been loosened or has fallen so
as
to endanger traffic ........ Where
there is any risk traffic must
be protected".
By 18th September
1996, Handbook 5 was no longer a group standard but was a code
of practice. In March 1996,
it was superseded by a document entitled "Railtrack Line
Specification: Track
Inspection Requirements" and given the number RT/CE/S/103
("S/1 03").
33. At
the time of the Ais Gill incident, the requirements for the examination of
structures
on the network were set out
in the group standard entitled "Examination of
Structures" and given
the number GC/EH0006.
In June 1995, that group
standard
was replaced by a new
standard also entitled "Examination of Structures" and in this
case given the number
GCIRT5121 ("Group Standard 5121"). For present purposes,
the relevant provisions
ofthis standard were as follows:
(i) Paragraph
4 of Part B which set out the underlying principle in the following
term:
"171e
principle of this document is
to ensure that all
structures which are in Rail/rack's ownership or which cross over or under
Rail/rack property are examined, either by visual or detailed examination with
more frequent routine obsen;ations, in accordance with laid down procedures,
and at intervals not exceeding those staled in this Railway Group
Standard".
13
(ii) A later passage in paragraph 4 of Part B in the following
terms:
"To comply with
these principles, the appropriate Director within Railtrack must ensure that:
·
a
programme for examination of all structures as defined in this Railway Group
Standard is drawn up;
• examinations are carried out according
to the programme;
·
the
findings of examinations are recorded and necessary actions taken ".
Reference to Table 1 appears
to show that a visual examination of, amongst other
things, rock cutting faces
is required at no greater than 12 monthly intervals. Part A
shows that full compliance
was to be achieved by 1 5t April 1996.
34. Two
matters of controversy relating to Group Standard 5121 were:
(i) Whether
the Group standard applied to rock cuttings at all;
(ii) If so, whether Handsworth Cutting was to be regarded as a rock
cutting.
These two matters are
considered under the heading "Reasons" below.
35. As
a response to the concerns raised by the incident at Ais Gill and the
subsequent
Inquiry Report, a new group
standard was developed, being the standard entitled
"Safe Asset Management
- Embankment and Cuttings" and given the number
GC/RT5151 ("Group
Standard 5151"). This standard was issued on 1st January 1996.
The relevant provisions are
as follows:
14
(i) Paragraph
4 in Part B sets out one ofthe principles as follows:
"The
risk from Slope Failure is minimised as far as reasonably practicable by
implementing auditable Examination, evaluation of the condition and maintenance
procedures".
(ii) A provision within paragraph 6.1 of Part B under the heading
"Requirements"
as follows:
"The
RDN must prepare and maintain a list of all embankments and cuttings with a
difference in level between top and bottom greater than 3m. The RDN must
clearly indicate those embankments and cuttings where signs of instability are
known to be present".
(iii) A further provision within paragraph 6.1 as follows:
"For
all those embankments and cuttings listed, the RDN must
(c) Consider carrying out an Examination
or implementing
appropriate
monitoring or actions; ...... "
(iv) A
provision within paragraph 6.2 in Part B under the heading "Frequency of
Examinations" as
follows:
"The
RDN must determine the frequency of Examinations based on the results of any
initial investigation and other subsequent evaluation of the condition or Slope
Failure ..... "
15
(v) A
provision in paragraph 6.4.2 of Part B under the heading "Evaluation of
Condition" relating to
locations where there has been no slope failure which
could affect the safety of
railway operations as follows:
"
..... the RDN must consider
initiating an evaluation of the condition
of the Embankment or
Cutting. Potential sources of information upon which such an evaluation is
initiated include:
• an Examination;
• evidence from historical records
(vi) Part A which showed that full compliance with the group
standard was to be
achieved by 1 st October 1996.
The Trackwalking Regime
36. In the months leading up to the derailment in September 1996,
the principal means by
which Railtrack provided for
inspection of the line was the trackwalking regime. This
was a system of long
standing and had been operated for many years by the British
Railways Board prior to rail
industry privatisation. After privatisation, the regime
was implemented by maintenance
contractors, such as Jarvis, using their Permanent
Way Maintenance teams.
37. The
essential features ofthe trackwalking regime in ] 996 were as follows:
(i) All
track was inspected at fortnightly intervals by a track inspector, who
physically walked along the
track for the purpose of observing any problems
with the condition of the
track and the adjacent verges, embankments and
16
cuttings.
Track inspectors would alternate between inspections, walking the up line one
week and walking the down line two weeks later. Every fourth inspection would
be undertaken by a track charge man, known as a Senior Track Examiner.
(ii) Track inspectors were made familiar with Handbook 5 and they
were required
to follow the guidance in
it. From 1 st March 1996 Handbook 5 continued to be
followed as a code of practice.
(iii) On completion of each inspection, a Track Examination Report
was prepared.
38.
In addition
to the trackwalking regime, it was the practice of Mr Turner and other
assistant section managers themselves to walk the track on a regular basis.
39.
All track
inspectors were required to demonstrate their competence to undertake
inspections either through proof of substantial experience within the industry
or by attending a track examination course. Track inspectors were not expected
to have any geotechnical knowledge.
40.
It is clear
that the track inspectors undertook their duties with diligence and took a
certain pride in their work. They sought to observe everything which could be
seen from the track. Nevertheless, the track was regarded as the main priority.
Track inspectors were not expected to observe anything which was not obvious.
17
41. Until
the Ais Gill incident, the railway industry worked on the basis that the
trackwalking regime was
entirely adequate in itself for the purposes of identifying
risks to safety due to the
condition of the track and associated embankments and
cuttings. After that
incident, a different approach was adopted which was eventually
to lead to the publication
of Group Standard 5151.
The Zonal Earthworks
Study and Associated Work
42. Mr
Cook was the Railtrack Director's Nominee ("RDN") for all group
standards and
he was the Structures
Engineer for LNEZ. When he became RDN, which was prior to
the incident at Ais Gill, a
decision was taken that the zone should establish its own
programme for monitoring and
maintenance of embankments. The result was that
Thorburn (amongst others)
were invited by LNEZ to tender for what became known
as the Zonal Earthworks
Study.
43. Tenders
were invited in July 1995. It follows that LNEZ initiated steps directed
towards the identification
and assessment of earthworks in advance of the publication
of Group Standard 5151 in
January 1996.
44. The
full title of the Zonal Earthworks Study was "Design of Zonal Earthworks
Assessment System & Earthworks Assessment Study 1995/96".
Clause 3 of the
specification for the study
detailed its scope, which included:
"conceptual
and development work to design, develop, supply, test and commission an
appropriate earthworks assessment system which will locate high risk earthworks
sites across the Railtrack London North Eastern Zone ".
18
The exercise was to include
a study ("the Pilot Study") to appraise the earthworks structures on
the following routes:
(i) Settle
Junction to Carlisle;
(ii) Skipton to Settle Junction to Carnforth;
(iii) Bradford Interchange to Halifax - Eastwood.
45.
Thorburn's
tender was accepted on 8th September 1995, the work was done in the
Autumn and a draft report was prepared dated ih December 1995. Following consultation, the
final report was published on 15th March 1996. The Pilot Study
covered 118 route miles, leaving 1,536 route miles within the zone to be
surveyed.
46.
During
discussions which followed the publication of the draft report, Thorburn were
invited to submit a proposal for a programme of work which would culminate in a
Strategic Review Report which would set out the most effective plan of action
to complete the earthworks study over the remaining 1,536 route miles of track
within the zone.
47.
On 30th
January 1996, Thorburn submitted their proposals set out in a document entitled
"Proposal for a Strategic Review" dated 29th January 1996.
That document summarised the proposed scope of work, the programme and the
anticipated costs. That cost was a relevant consideration to the project is
clear from the following passage included in Thorburn's proposals:
19
"This
will enable the most effective strategy in terms of identifying high risks
sites commensurate with the costs of doing so and the consequences of any
failures at the sites to Railtrack LNE".
48. At
about the same time and in response to similar invitations, Thorburn submitted
proposals for a Rock Cutting
Pilot Study and for the inspection of certain high risk
sites. In due course,
Thorburn were instructed to proceed with the works which was
the subject of all three
proposals.
49. As
regards the strategic review, Thorburn submitted their final report dated 1 ih April
1996 and entitled
"Report on Review of Strategy Regarding Earthworks Structures"
("the Strategic
Review"). In short, Thorburn recommended that walkover surveys
should be undertaken at all
sites in accordance with a 5-year programme. Paragraph
5.1 of the final report
under the heading "Recommendations" reads as follows:
"5.1 Based on a five year overall programme for
completion of the Zonal Earthworks Structural Asset Database, the following
table summarises the recommended year by year actions to provide the most cost
effective risk reduction during that period. In general, it is recommended that
specific problem sites are inspected first, in order to expeditiously instigate
remedial measures where necessary. Such sites should be dealt with generally in
order of commercial priority.
Year 1 1996-97
Targeted
inspections of problems sites as identified by PWME, generally in order of
commercial priority.
Desk
study to identify sites most likely to prove problematical based on topography
(i.e. cuttings on sidelong ground) and start of inspection of same, again based
on commercial prioritisation.
Cataloguing of reports formerly held by Soil Mechanics
Section and subsequent cross referencing of these reports Ivith both the
targeted
20
sites mentioned above and
previously surveyed routes.
Start
of desk study to complete geometric database from Line Plans, aerial
photographs etc., wherever possible.
Year 2 1997-98
Years 3-5 1998-2001
Completion of targeted
site inspections.
Completion of desk study
work on geometric database.
Start
of site walkover of remaining routes, generally in order of commercial priority
(Approx. 300 miles per year).
Completion of site
walkovers (Approx. 300 miles per year) ".
There was to be a desk study
to identify sites to be prioritised. At such sites, there
was to be a walkover survey
in either Year 1 or Year 2. For other sites, the first
walkover survey might take
place in Year 2, Year 3, Year 4 or Year 5.
50. That
cost considerations remained a factor in the strategy recommended by Thorburn
is apparent from the
following references in the Strategic Review:
(i) In
paragraph 1 under the heading "Introduction", the following:
"The
aim of the review is to determine the most cost effective
approach to completing the Earthworks Asset Survey commenced in 1995, and to reducing the risk of
further earthworks failures of the types mentioned earlier n.
(ii) In paragraph 4.3.4 under the heading "Prioritisation of
Future Maintenance
Schemes", the
following:
21
"On
the basis that Railtrack LNE Zone does not have unlimited funds to deal with
earthworks on a year by year basis, it is therefore crucial that the budgets
available are spent as effectively as possible. With regards to earthworks,
this means achieving the greatest reduction in exposure to risk of earthworks
failures and associated loss of revenue from train operators per pound spent.
This therefore leads on to the two main factors to be considered in determining
the cost effectiveness of any future maintenance work:
1. The commercial importance of the route.
2. The likelihood of failure of the
structure.
A
mechanism must therefore be developed to allow these two factors to be assessed
in an objective way, permitting the level of risk reduction offered per pound
spent to be calculated on a site by site and scheme by scheme basis.
It follows then that two
identical schemes on two different routes can be easily prioritised on the
basis of these commercial considerations ".
Inspection
ofHandsworth Cutting prior to lsth September
1996
51. For
many years, Handsworth Cutting had been subject to the trackwalking regime.
Mr Burgess was familiar with
Handsworth Cutting and had walked the track on many
occasions. He was aware of
the rocks but thought that the risk of rock falling onto the
track was very low because
of the slope and because of the depth and width of the
cess. Mr Burgess had walked
the track in that location two days before the derailment
on 16th September
1996. His Track Examination Report No. 8451 shows that he
observed nothing untoward.
52. However,
Handsworth Cutting was not subject to any other relevant form of
inspection or examination.
Thus:
22
(i) It
was not part of the Pilot Study undertaken in Autumn 1995 as part of the
Zonal Earthworks Study.
(ii) It was not regarded as a rock cutting and was, accordingly,
not part of the
Rock Cutting Pilot Study
proposed by Thorburn and implemented in 1996.
(iii) It was not one of the High Risk Sites which had been
identified ion the Zonal
Earthworks study.
(iv) It was not included in a programme for examination pursuant to
Group
Standard 5121.
(v) It
was not identified as requiring a targeted site inspection in accordance with
the recommendations set out
in Thorburn's Strategic Review.
(vi) RaiItrack had not prepared a list of embankments and cuttings
with a
difference
in level between top and bottom greater than 3m in accordance with paragraph 6.1
of Group Standard 5151. It follows that Handsworth Cutting did not appear on
any such list, Railtrack had not considered carrying out an examination or
implemen6ng appropriate monitoring and Railtrack had not determined the
frequency of examinations.
On the
other hand, Railtrack did consider initiating an evaluation of the condition of
Handsworth Cutting within the meaning of paragraph 6.4.2 of Group Standard
5151, such consideration being the subject of Thor bum's Strategic Review.
23
ALARP
53.
It was ATN's
case that it was Railtrack's obligation in relation to Handsworth Cutting to
take steps to ensure that the risks to health and safety associated with the
use of the network were kept as low as reasonably possible. That expression is
commonly reduced to the acronym ALARP.
54. In
this context, A TN maintained specifically:
(i) Firstly,
that Railtrack ought to have procured an urgent series of walkover
surveys of all of the
embankments and cuttings in the North Eastern Zone within about 12 months after
January 1995; and
(ii) Secondly, that if Handsworth Cutting had been subjected to
such a walkover
survey,
then the derailment would have been avoided because the instability in the
sandstone ledge from which the boulder fell on the night of 1 ih September 1996 would be likely to have been
identified as unstable and remedial action taken.
As to
the second of these two propositions, there is common ground. Jt was accepted
that, if a walkover survey had been undertaken, then it is likely that it would
have been undertaken by or participated in by someone with geotechnical
knowledge. Further, it was accepted that such an individual would have
identified the sandstone ledge as potentially unstable. Further, it was
accepted that, if such ledge had been
24
identified
as unstable, then remedial action to dislodge the unstable parts of the rock
could have been undertaken directly just as similar work was undertaken
immediately following the derailment in September 1996 and on subsequent
occasions.
55.
There were
issues between the parties as to whether it was practicable for Railtrack to
procure walkover surveys of all cuttings and embankments within the period
suggested. Railtrack accepted that cost was not a relevant consideration.
However, it was not accepted that Railtrack could have been expected to start
in January 1995 and it was suggested that there were a number of reasons why it
was impracticable to achieve the task within a 12 month period.
56.
As indicated
above, what actually happened was that, following rail industry privatisation,
no relevant steps were taken until the occurrence of the incident at Ais Gill
in January 1995. Even then, no relevant steps were taken until July 1995 when
Railtrack invited tenders for the Zonal Earthworks Study. A TN's case was that
Railtrack should have started earlier and acted differently~ As to the start
date, ATN said Railtrack should have started in January 1995 and before the Ais
Gill incident. As to the action to be taken, A TN maintained that Railtrack should
have instituted an urgent programme of walkover surveys throughout the zone
rather than procuring an independent study of the problem. ATN's case was that,
if the study of the problem was required, it should have been undertaken in the
period between rail industry privatisation in April 1994 and the end of that
year. Underlying A TN's case was the implicit suggestion that too much regard
had been given to commercial considerations which resulted in delay.
25
57.
As to the
time required for the walkover surveys, ATN relied on the evidence of their
expert, Dr Clark. He was entirely convinced that the 1,536 route miles which
remained unexamined after the Zonal Earthworks Study could have been surveyed
in much less than the 5-year period contemplated by Thorburn in the Strategic
Review.
58.
On the basis
of the Pilot Study, Dr Clark identified a realistic coverage by the survey
teams of 30 miles per team week. On this basis, using 2 teams, Dr Clark
inferred that the remaining 1,536 route miles would take some 26 weeks to
survey. Using this figure, Dr Clark's view was that the entire exercise could
and should be completed within 12 months, allowing 6 months for the walkover
surveys, 3 months beforehand for preparation in the nature of a desk study and
3 months afterwards for collation of results.
59.
The
difficulties foreseen by Railtrack in achieving the task within that timescale
were explained by its expert, Mr Laird, when he came to give evidence. Mr
Laird's view was that such surveys could not practicably be undertaken during
the Summer months because excess vegetation would obscure the surveyors' view.
He regarded the months of October to March (inclusive) as "the inspection
season" and he expressed the view that a minimum of two such seasons would
be required to survey the 1,536 route miles in question. In this context, Mr
Laird expressed the view that surveyors would be inhibited by bad weather
during the October to March period and that there was a shortage of suitably
qualified personnel to undertake such surveys in 1996.
26
60.
In
cross-examination, Mr Laird expressed the view that, ideally, during site work,
each team would work one week on, one week off On this basis, he agreed that
using 4 teams the site work could have been completed in just 24 working weeks.
Later, summarising, Mr Laird said that if the proposal had been raised in July
1995 then he agreed the site work could have been completed in 6 months.
61.
Later still,
in re-examination, Mr Laird was inclined to suggest that his 6 month period did
not allow for such matters as difficulties in obtaining possessions and the
shortage of suitably qualified staff In the circumstances, this was surprising
because Mr Laird had expressly adverted to the shortage of qualified staff when
giving evidence in chief Furthermore, the difficulty in obtaining possessions
was a factor which applied equally to the Pilot Study, which formed the basis of
the assessment with which Mr Laird had been invited to agree and had agreed.
62.
On these
issues, I prefer Railtrack's case on the start date but I prefer the evidence
of Dr Clark as to the time required to complete the walkover surveys. As to the
start date, I am conscious that it was essential, in practice, for Railtrack to
take independent advice about how best to survey the relevant cuttings and
embankments. Given the length of time which is often required to procure such
advice, I am not persuaded that it was practicable for Railtrack to commence
the survey process earlier than July 1995. In terms of the time required
thereafter to procure walkover surveys of the remaining 1,536 route miles of
track, I accept Dr Clark's evidence that 12 months would have sufficed and that
the exercise could have been undertaken and completed by the end of June 1996.
Had the exercise been undertaken during that period, then, following Dr Clark's
expected split of the activities required, the desk study could
27
have been undertaken in
July, August and September 1995; the site work could have
been undertaken in the
inspection season favoured by Mr Laird between the months
of October 1995 and March
1996; and the data could have been collated in the three
months April, May and June
1996. Finally, I find that, had such steps been taken, the
derailment would have been
avoided because the loose material in the sandstone ledge
on the upside of Handsworth
Cutting from which the boulder eventually fell on the
night of 1 ih September 1996 would by that time already
have been removed.
REASONS
HSWA
63. The
first issue is whether the indemnity set out in Clause 8(2) of the Track Access
Agreement is triggered by
breach on Railtrack's part prior to 18th September 1996 of
the obligations imposed by
sections 2 to 4 of HSW A and paragraph 3 of the 1992
Regulations. The terms of
Clause 8(2), so far as material, are as follows:
"8.2 Railtrack shall
indemnify the Train Operator ..... against all damage,
losses,
claims ...... incurred or suffered
by the Train Operator:
(a) as a result of a failure by Railtrack to
comply with its
obligations under the
Safety Obligations; n
The terms of sec60ns 2 to 4
of HSW A, so far as material are set out in paragraph 25
above. The terms of
paragraph 3 of the 1992 Regulations, so far as material, are set
out in paragraph 26 above.
28
64. On
this issue, Railtrack raised a preliminary point. Essentially it argued that
because
Part 1 of HSW A was not such
as to confer a right of action in civil proceedings it
should not be regarded as
giving rise to safety obligations within the meaning of the
Track Access Agreement.
65. In
support of this point, Railtrack referred to Section 47(1) of HSW A which is in
the
following terms:
"(I) Nothing in this
Part shall be constrned:
(a) as conferring a right of action in any
civil proceedings in
respect of any failure to
comply with any duty imposed by section 2 to 7 or any
contravention of section 8 n.
66. The
indemnity set out in Clause 8(2)(a) of the Track Access Agreement relates to
damage caused by failure on
Railtrack's part to comply with its safety obligations.
Such obligations are defined
in Clause 1.1 of the Track Access Agreement as follows:
"
"Safety Obligations n
means all applicable
obligations and laws concerning health and safety (including any duty of care
arising at common law, and any arising under statute, statutory instrument, or
mandatory codes of practice) in Great Britain n.
From that definition it is,
in my view, clear that the obligations in question are not
limited to obligations
breach of which gives rise to a claim in civil proceedings. They
include obligations, breach
of which is justiciable only in the Criminal Courts.
29
67.
As to Section
47(1) of HSWA, that provision does not more than to show that Part 1 of HSW A
does not, of itself, give rise to a claim in civil proceedings. It says nothing
about whether it is open to parties to contract on the basis that the rights
and duties between themselves will be regulated by reference to whether or not
an obligation imposed by Part 1 has been complied with. In my view, it is open
to parties to contract on that basis.
68. For
these reasons, I reject Railtrack's preliminary point.
69.
In developing
ATN's case on this first issue, Mr Jackson relied on the duties imposed by
Sections 2 to 4 of HSW A and paragraph 3 of the 1992 Regulations which are set
out in paragraphs 26 and 27 above.
70.
In the course
of argument, it became clear that the main thrust of ATN's case depended upon
sub-sections 2(1) and 3(1). This is because the duties set out in Section 4 and
paragraph 3 are less onerous. Since, in my view, Section 4 and paragraph 3 for
present purposes add nothing to sub-section 2(1) and 3(1), the following
discussion addresses the latter.
71.
In respect of
sub-sections 2(1) and 3(1), Mr Jackson contended that the obligation to ensure
safety which was imposed was absolute subject to the qualification introduced
by the expression "so far as is reasonably practicable n. For this contention, he relied upon the observations
of Lord Goff in Austin Rover Group Limited v. Her Majesty's Inspector of
Factories (1990) 1 AC 619 (a case decided under Section 4 of HSW A) as
follows (page 627):
30
"Subject
to the limited qualification embodied in the phrase "so far as is
reasonably practicable," it seems to me that the duty imposed upon the
Defendant to ensure that the relevant premises are safe and without risks to
health for any use for which they are made available is prima facie
absolute".
72. Much
of Mr Jackson's argument was directed towards the test to be applied in
determining whether any
particular measure which could have been undertaken was
one which was to be regarded
as reasonably practicable and, therefore, one which
should have been taken. In
summary, his contention was that, in respect of such a
measure, a balancing
exercise had to be undertaken, weighing foreseeability, in the
sense of the likelihood of
the incidents of the relevant risk, in one side of the scale,
against the inconvenience of
taking the measure necessary to eliminate or reduce the
risk (including the costs
involved) in the other. Then, so Mr Jackson's contention
went, the relevant measure
had to be implemented unless the inconvenience was
grossly disproportionate to
the risk involved. In support of this contention, Mr
Jackson relied upon Edwards v. National Coal Board (1949) 1 All ER 743 (a case
decided under Section 49 of
the Coal Mines Act 1911) as well as relying on the
observations of Lord Goff in
the Austin Rover case (page 625).
73. In
practice, Railtrack appear to accept these contentions. They expressly adverted
to
the "gross disproportion" test in their Railway Safety Case dated
March 1996
(paragraph 6.15).
31
74. I
also accept these contentions.
75.
In paragraph
62 above, I have found that it was practicable for Railtrack to undertake an
urgent series of walkover surveys covering the remaining 1536 route miles of
the North Eastern Zone within the 1995/1996 inspection season.
76.
As to
foreseeability, I recognise that the specific and rather unusual and surprising
sequence of events which gave rise to the derailment which occurred on 18th
September 1996 was not itself foreseeable. On the other hand, I hold that the
risk of physical harm both to Railtrack's employees and to others not in their
employ who might be using the network was foreseeable as a result of rockfalls
from a cutting such as Handsworth Cutting.
77.
Accordingly,
when a balance is struck between the risk involved and the inconvenience of
arranging the urgent series of walkover surveys to which I have referred (and
bearing in mind that Railtrack accept for present purposes that cost is not a
relevant consideration), the inconvenience is plainly not disproportionate to
the risk at all, let alone being grossly disproportionate. For this reason, I
hold that subsections 2(1) and 3(1) required that the urgent series of
walkover surveys should have been undertaken in the 1995/1996 inspection season
(if not before) and that Railtrack's failure to do so amounted to a breach not
only of its duties pursuant to those sub-sections but also of Safety
Obligations within the meaning of Clause 1 (1) and Clause 8(2) of the Track
Access Agreement.
32
78.
In the light
of these conclusions, I therefore hold that the indemnity set out in Clause
8(2) of the Track Access Agreement is triggered by Railtrack's failure to
undertake such urgent walkover surveys.
Group
Standards
79.
Introduction:
The
second issue is whether the indemnity set out in Clause 8(2) of the Track
Access Agreement is triggered by failure on the part of Railtrack to comply
with group standards. The matters relied on are addressed under separate
sub-headings below.
80.
Handbook 5:
A TN
relied on Clause 3.1 in Section C, the terms of which are set out in paragraph
32(ii) above. It was suggested that Railtrack had failed to carry out the
required examinations at Handsworth Cutting. In reply, Railtrack relied upon
the inspections made pursuant to the trackwalking regime. The issue between the
parties was whether such inspections amounted to and were sufficient to fulfil
the obligation to carry out the examinations required by the handbook. In this
context, ATN's contention was that Clause 3.1 implied a regime amounting to
more than the observations made by track inspectors in the context of the
trackwalking regime. I accept this contention. Clause 3.1 plainly contemplates
that special visits will be made to cuttings after severe frost, heavy rainfall
or snow thaw. Furthermore, Clause 3.1 also contemplates that any rock in
cuttings will be checked so as to determine whether the material has been
loosened. The trackwalking regime did not provide for either of these. Given
that there were no other inspections of Handsworth Cutting, I find that
Railtrack failed to comply with Clause 3.1. However, it is necessary to
33
remember that Clause 3.1 was
contained in Handbook 5 and was not reproduced in S/1 03 when that document
replaced the handbook as the relevant group standard in March 1996. It lost the
status of a group standard. Accordingly, the detachment and fall of the boulder
on the night of 1 ih September 1996 could not on this score be regarded as
having been caused by a failure to comply with group standards unless it was
caused by a failure which occurred prior to March 1996. There was no evidence
directed to this point. It seems to me that there is a material distinction
between the kind of examination contemplated by Clause 3.1 and the kind of
examination involved in a walkover survey such as I have held should have been
undertaken between October 1995 and March 1996. Specifically, the walkover
survey would have involved an assessment by an individual with geotechnical
qualifications not only as to the present state of any rock but also as to any
likely future deterioration. By contrast, an examination such as is contemplated
by Clause 3.1 could properly have been undertaken by an individual without
formal qualifications, such as one of the track inspectors engaged in the
trackwalking regime, who would be required to ascertain the present condition
of any rock but would not be expected to direct his mind towards the
possibility of future deterioration. I am not persuaded that an examination
pursuant to Clause 3.1 undertaken prior to March 1996 would necessarily have
identified a loosening of the rock at the sandstone ledge from which the
boulder eventually fell. Accordingly, whilst I hold that Railtrack were in
breach of Clause 3.1, I am not persuaded that that breach was causally
connected with the derailment which occurred.
34
81. Group
Standard 5121:
ATN relied on the provisions
of Group Standard 5121, which is summarised in
paragraph 33 above, and
contended that Handsworth Cutting constituted a rock
cutting which ought to have
been subjected to a regime of visual inspection at no
greater than 12 monthly
intervals. A TN's case was that Handsworth Cutting should
have been included in a
programme which itself should have been put in place by 1 st
April 1996. It is common
ground that Handsworth Cutting was not included in any
such programme. However,
even if it had, that would in my view not necessarily
have avoided the derailment.
Such a programme could, even on A TN's case, properly
have provided for visual
inspection of Handsworth Cutting at any time during the 12
months following 1 st April 1996. It follows that the inspection
might, in any event,
have come too late to avoid
the incident which occurred on 18th September 1996. For
these reasons, I hold that
there was no relevant breach of Group Standard 5121.
82. Group
Standard 5151:
In the context of Group
Standard 5151, A TN relied, firstly, on paragraph 4 in Part B
which identified the
principles adopted, including the following:
"The
risk from Slope Failure is minimised as far as reasonably practicable by
implementing auditable examination, evaluation of the condition and maintenance
procedures".
A TN contend that Railtrack
[ailed to implement the procedures referred to. I do not
regard this part of Group
Standard 5151 as imposing any freestanding obligations,
independent of the remaining
text. Rather, it seems to me that the object of paragraph
4 is to identify the
principles adopted so as to enable industry users to interpret the
other passages in the group
standard appropriately.
35
83.
The main
thrust of ATN's case on Group Standard 5151 centred around the obligations set
out in paragraph 6.1 and 6.2 of Part B, which are set out in paragraph 35
above. The heart of this part of ATN's case was that RaiItrack had failed to
prepare a list of all embankments and cuttings with a difference in level
between top and bottom greater than 3m. On ATN's case, it followed from this
that RaiItrack had failed to undertake the other obligations imposed in respect
of listed embankments and cuttings, such as the obligation to consider
examination and monitoring and the obligation to determine the frequency of
examinations. However, it is cle'lr to me that, by 18th September
1996, the deadline for compliance with Group Standard 5151 had not yet been
reached. Part A requires full compliance only by 15t October 1996.
It is impossible to say there was a failure to comply at a time when the date
for compliance had not yet been reached.
84.
The third
part of A TN's case on Group Standard 5151 related to paragraph 6.4.2 of Part
B, set out above in paragraph 35(v). In relation to locations where there had
been no slope failure, Railtrack, through the RDN, were to consider initiating
an evaluation of the condition of the cutting. I have already found that
Railtrack did give consideration to that matter, that being the subject of the
Strategic Review. Accordingly, I reject A TN's case on this point.
85. For
these reasons, I hold that there was no relevant breach of Group Standard 5151.
36
86.
Conclusion:
For the
reasons set out in the preceding paragraphs under this heading, I hold that the
indemnity set out in Clause 8(2) of the Track Access Agreement was not
triggered by any failure on Railtrack's part to comply with group standards.
Tort
87.
The third
issue is whether Railtrack were in breach of their duty of care so as to
trigger the indemnity set out in Clause 8(2) of the Track Access Agreement
and/or liability to A TN in tort.
88.
Railtrack
accepted that they owed a duty of care to users of the railway infrastructure
including A TN.
89.
ATN's case
was that Railtrack were in breach of that duty of care in failing to implement
an urgent programme of walkover surveys in sufficient time to ensure that
remedial work was undertaken at Handsworth Cutting such as to make safe the
sandstone ledge on the up side.
90.
I take the
view that, after the incident at Ais Gill, Railtrack's duty of care certainly
required them to take such steps as were reasonable in all the circumstances to
assess the condition of all cuttings and embankments on the network. In my
view, for present purposes, the key question is whether that obligation
required an urgent programme of walkover surveys with site work being
undertaken in the 1995/1996 inspection season or whether some of the surveys
might reasonably have been deferred until the following year. The point is
that, if any surveys were deferred until
37
the following year, then the
survey of Handsworth Cutting might have been one of them and, in that event,
the survey would have been too late to prevent the derailment.
91.
I am not
satisfied that Railtrack's duty of care was such as to require that all
walkover surveys be completed in the 1995/1996 inspection season. Accordingly,
I hold that there was no relevant breach ofRailtrack's duty of care.
Other Defences
92.
Had I been
minded to hold Railtrack liable on the basis that the trackwalkers regime
failed to fulfil their obligations under Handbook 5, Mr. Solomon invited me to
consider a defence of estoppel based on the proposition that it was A TN
itself, in a previous guise, that had instituted the trackwalking regime in the
first place.
93.
In the
alternative, if I was minded to hold Railtrack liable on the basis of shortcomings
in the trackwalking regime, Mr Solomon maintained that liability for such
shortcomings did not transfer to Railtrack by virtue of Clauses 10.2.2 and
10.3.2 of the Railtrack Transfer Scheme.
94.
Since I have
not held Railtrack liable on the basis of shortcomings in the trackwalking
regime, these defences do not arise.
Quantum and Interest
95.
Subject to
one issue, the parties reached agreement as to the amount of A TN's claim and
as to the amount of interest payable.
38
96.
The issue
related to the period over which Railtrack ought to pay interest.
Specifically,
Mr Solomon, on Railtrack's behalf, submitted that ATN should not recover
interest during the period between 16th July 1997 and 16th
August 1999 because that represented a period during which ATN had failed to
prosecute the claim with due diligence.
97.
In support of
this contention, Mr Solomon pointed out that ATN received a copy of the
Officer's report into the derailment on 16th July 1997 and could
therefore have been expected to initiate dispute resolution procedures at or
about that date. He went on to point that A TN did not in fact refer the matter
to mediation until 16th August 1999.
98.
It seems to
me that the matters upon which Mr Solomon relies do evidence some lack of
enthusiasm in prosecuting the claim. On the other hand, Railtrack have had the
use of the money throughout the relevant period, whilst ATN have been out of
pocket.
99.
I take the
view that, in the exercise of my discretion to award interest to the successful
party, I should award interest to A TN to cover the period 16th July
1997 to 16th August 1999 as well as the other periods.
100.
Accordingly, J hold that the sums due to ATN are the principal sum of £160,523.82 and
interest in the sum of £55,657 .42, making a total of £216, 181.24.
39
AWARD
101. In the light of the
findings and for the reasons set out above, I order, by way of
interim award, that:
(i) Railtrack
shall within 28 days of the date of this award pay A TN the sum of
£160,523.82 pursuant to
Clause 8.2 of the Track Access Agreement.
(ii) Railtrack shall within 28 days of the date of this award pay A
TN the sum of
£55,657.42 by way of interest
pursuant to Section 49 of the Arbitration Act
1996.
(iii) All other issues in this arbitration (including the liability
for costs and my fees
and expenses) and the power
to make any further award or awards in respect
thereof are reserved to me.
MADE AND PUBLISHED at
Keating Chambers, 10 Essex Street, London, WC2R 3AA.
Dated this 5th
day of December 2001.
![]()
Witnessed
by: .; ~ .
Name: ....... a-C?M~ ....... M.l!.r:-!.T~ .
Address: ke;:~TNt;i .. ~4: f!;.~~ .
................
!.~ .. ~.~~ .. ?T .
.
. .. . .. . .. . .. ~.r:-J.;c>.
~. ~ .
WC2(L 3AA
..............................................................
40
John Marrin Q.C Arbitrator